25 Strawberry Road Mike and Sarah Smith

Project Description

Welcome to a demo of our digital dashboard! Scroll down to:

  • gain visibility and control of the works for an ongoing project
  • understand all the project and follow its progress
  • review pictures and videos in real time for each site visit
  • ask questions in context about project details
  • track old conversations on past phases of the work
  • monitor the schedule of works for each phase, in detail
  • control the budget consumption compared to the cost breakdown

This demo is based on a real project of a three storey terraced house that included a loft conversion, side extension and full house renovation. This space in a real project dashboard is used for a description of the project

Documents

Project Progress

80%

Payment Rate

73%

95,000.00/130,000.00£

Project Timing

  • Start
    Jan 16 2017
  • End
    Mar 31 2017

01/16/2017 03/31/2017

100%

Overall Project Completion

  • Structural Frame and Roofs

    20%
  • Plastering of Walls and Ceilings

    60%

80%

  • 40%

    Suspended Timber Floor and Stud Walls

  • 80%

    Second Fix Electrics and Plumbing

20%

Structural Frame and Roofs

40%

Suspended Timber Floor and Stud Walls

60%

Plastering of Walls and Ceilings

80%

Second Fix Electrics and Plumbing

1. Site Set Up and Scaffolding Complete 100%

100%
Description
Secure site, fence, sings and notices, check existing services, CDM, health and safety, first aid, amenities for workers.

2. Demolition of walls and Roof Complete 100%

100%
Description
Removal of rear part of the pitched roof to allow for the construction of the dormer.
947
944

3. Roof Structure, Dormer and Covering Complete 80%

80%
Description
Re-roofing of rear roof. Strengthening of Existing front pitch roof, flat roof and dormer walls.  
img_7953img_7957 img_7952 img_7951
946

4. Joinery First Fix Complete 100%

100%
Description
Stud Walls and suspended timber floor and staircase  
942
941
971
970
956
953

5. Electrical and Plumbing First Fix Complete 100%

100%
Description
Wiring and piping of the top floor.
991
989
985

6. Joinery 2nd Fix and Plastering Complete 95%

95%
Description
Plasterboards, insulation and plastering of the walls
992
990
987
986
985
984

7. Plumbing and Electrical 2nd Fix Complete 40%

40%
Description
Plumbing connections and installation of sockets, switches and light fixtures

8. Internal Fitting Out Complete 30%

30%
Description
Installation of finishes like Sanitary Ware, Windows and Doors

Project Discussion 2 Responses to 25 Strawberry Road

  1. Hi guys,

    thank you very much for today’s meeting. Can you please remind me when the windows are going to be delivered?

    Thanks,
    Sarah

    27th February 2017 at 11:25 pm
    Sarah
    • Hi Sarah,

      sure, they will be delivered on 6th March, we have a 3 hour slot for now between 8AM and 11AM; we will have a more precise time on the delivery day.

      Regards,
      Vinz

      27th February 2017 at 11:28 pm
      Vinz